Question 128

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Mar 6, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Mar 10, 2026
They give you a competitive edge and help you prepare better.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Mar 4, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Mar 28, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Mar 13, 2026
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 129

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

Options:

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Discussion
Question 130

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Discussion
Question 131

Which should define how tools will be used to support the information needs of the project team?

Options:

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Discussion
Page: 32 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99