PRINCE2 Updated Prince2-Foundation Exam Questions and Answers by jana

Page: 32 / 34

PRINCE2 Prince2-Foundation Exam Overview :

Exam Name: PRINCE2 7 Foundation written Exam
Exam Code: Prince2-Foundation Dumps
Vendor: PRINCE2 Certification: PRINCE2 Certification
Questions: 461 Q&A's Shared By: jana
Question 128

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Discussion
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 12, 2024
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Question 129

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

Options:

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Discussion
Question 130

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Discussion
Question 131

Which should define how tools will be used to support the information needs of the project team?

Options:

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Discussion
Page: 32 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99