Question 116

In which process are the key decisions to control the project made?

Options:

A.

Directing a project

B.

Initiating a project

C.

Managing a stage boundary

D.

Controlling a stage

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Sep 4, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Sep 16, 2026
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Sep 6, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Sep 21, 2026
Me too. They're a lifesaver!
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Sep 19, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 117

Which TWO are objectives of the 'closing a project’ process?

1. To confirm to the project board that each stage’s products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Discussion
Question 118

Which is a description of a purpose of the 'managing product delivery’ process?

Options:

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Discussion
Question 119

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

Options:

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Discussion
Page: 29 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$31.5  $104.99

Prince2-Foundation Testing Engine

$37.5  $124.99

Prince2-Foundation PDF + Testing Engine

$49.5  $164.99