Question 124

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

Options:

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Question 125

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

Options:

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

Discussion
Question 126

What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

Options:

A.

Performance target

B.

Project baseline

C.

Integrated elements

D.

Project context

Discussion
Question 127

How is uncertainty identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Discussion
Page: 31 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99