PRINCE2 Updated Prince2-Foundation Exam Questions and Answers by renee

Page: 21 / 34

PRINCE2 Prince2-Foundation Exam Overview :

Exam Name: PRINCE2 7 Foundation written Exam
Exam Code: Prince2-Foundation Dumps
Vendor: PRINCE2 Certification: P3O
Questions: 471 Q&A's Shared By: renee
Question 84

Which is a purpose of the Closing a Project process?

Options:

A.

Authorize the final stage of the project

B.

Confirm that all benefits defined in the Business Case have been achieved

C.

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.

Delegate day-to-day management of the end of the project to the Project Manager

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Nov 14, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 4, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Nov 7, 2025
Me too. They're a lifesaver!
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Nov 26, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Nov 27, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 85

Which is part of quality control?

Options:

A.

Undertake quality reviews

B.

Write Product Descriptions

C.

Provide assurance that the project is being conducted properly

D.

Document the customer's quality expectations

Discussion
Question 86

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options:

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Discussion
Question 87

Which plan provides the Business Case with costs during the Initiating a Project process?

Options:

A.

Initiation Stage Plan

B.

Project Plan

C.

Stage Plan

D.

Team Plan

Discussion