Question 28

According to PRINCE2, which characteristic is necessary for an effective project board?

Options:

A.

An ability to delegate

B.

An attention to detail

C.

A calm management style

D.

A 'problem-solving' approach

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Jul 21, 2025
Yeah, definitely. I experienced the same.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jul 13, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jul 6, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Jul 8, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Question 29

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

Options:

A.

The senior user's responsibilities for realizing benefits

B.

Statements of actual versus forecast benefits at reviews

C.

The management actions needed to ensure benefits are realized

D.

No specific documents related to benefits are necessary

Discussion
Question 30

Which is a purpose of a project brief?

Options:

A.

To act as a base document which enables the project board to assess progress

B.

To provide a sound basis for project initiation

C.

To define how the achievement of the project's benefits can be measured

D.

To provide a description of the means and frequency of communication

Discussion
Question 31

Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

Options:

A.

Project Assurance

B.

Project Support

C.

the risk actionee

D.

the risk owner

Discussion
Page: 7 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99