Question 100

What product defines the reporting requirements between the Project Manager and Team Manager?

Options:

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Discussion
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Nov 14, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Nov 9, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Nov 25, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Nov 12, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Question 101

Which does the Executive need to ensure is in place before the project is initiated?

Options:

A.

All Work Packages are authorized

B.

An understanding of how the project will contribute to corporate objectives

C.

The Project Plan has been approved

D.

The Project Initiation Documentation is complete

Discussion
Question 102

Which is a true statement about time-driven controls?

Options:

A.

Time-driven controls are used for monitoring the progress of Work Packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An Exception Report is a time-driven control

Discussion
Question 103

Which is a typical core activity within configuration management?

Options:

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Discussion
Page: 25 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99