Question 68

What 15the purpose of the ‘progress! practice?

Options:

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 2, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 1, 2026
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Sep 6, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 16, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 69

When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.

Which principle is being applied by the project manager when reviewing this information?

Options:

A.

Learn from experience

B.

Tailor ta Suit the project

C.

Manage by stages

D.

Ensure continued business justification

Discussion
Question 70

Which is an objective of the ‘directing a project’ process?

Options:

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Discussion
Question 71

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Discussion
Page: 17 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$31.5  $104.99

Prince2-Foundation Testing Engine

$37.5  $124.99

Prince2-Foundation PDF + Testing Engine

$49.5  $164.99