Question 76

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Discussion
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Nov 18, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Nov 8, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Nov 10, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Nov 9, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Nov 16, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Question 77

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

Options:

A.

Product Description

B.

Team Plan

C.

Work Package

D.

Stage Plan

Discussion
Question 78

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Discussion
Question 79

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Discussion
Page: 19 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$42  $104.99

Prince2-Foundation Testing Engine

$50  $124.99

Prince2-Foundation PDF + Testing Engine

$66  $164.99