Question 88

The prime purpose of configuration management is to:

Options:

A.

ensure the traceability and integrity of the delivered product or products

B.

minimise the impact of changes on the scope of the project

C.

ensure that the final product meets the needs of the business as defined by key stakeholders.

D.

maximise the impact of agreed enhancements to the project deliverables

Discussion
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Dec 25, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Dec 11, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Dec 25, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Dec 5, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Dec 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Question 89

A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.

Options:

A.

a hybrid.

B.

an extended.

C.

a reduced.

D.

a combined.

Discussion
Question 90

In order to be defined as an issue, which of the following conditions must be satisfied?

Options:

A.

It must result in a set tolerance being exceeded.

B.

The project manager must be able to resolve it.

C.

It must have happened because of an identified risk.

D.

The project team must be able to deal with it internally.

Discussion
Question 91

Which of the following responsibilities lies with the project management office?

Options:

A.

Liaising with end users.

B.

Managing suppliers.

C.

Providing technical support.

D.

Supporting the project sponsor.

Discussion