Question 88

The prime purpose of configuration management is to:

Options:

A.

ensure the traceability and integrity of the delivered product or products

B.

minimise the impact of changes on the scope of the project

C.

ensure that the final product meets the needs of the business as defined by key stakeholders.

D.

maximise the impact of agreed enhancements to the project deliverables

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Nov 11, 2025
That's great to hear. I am going to try them soon.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Nov 4, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Nov 3, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Nov 12, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Question 89

A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.

Options:

A.

a hybrid.

B.

an extended.

C.

a reduced.

D.

a combined.

Discussion
Question 90

In order to be defined as an issue, which of the following conditions must be satisfied?

Options:

A.

It must result in a set tolerance being exceeded.

B.

The project manager must be able to resolve it.

C.

It must have happened because of an identified risk.

D.

The project team must be able to deal with it internally.

Discussion
Question 91

Which of the following responsibilities lies with the project management office?

Options:

A.

Liaising with end users.

B.

Managing suppliers.

C.

Providing technical support.

D.

Supporting the project sponsor.

Discussion