Question 12

How is the deployment baseline used throughout the project?

Options:

A.

Progress monitoring and implementation of change control.

B.

Benefits realisation.

C.

Identify options for deployment.

D.

Prepare users for delivery of the output into operation.

Discussion
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Sep 14, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 15, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Sep 22, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Sep 10, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 14, 2025
Great. Yes they are really effective
Question 13

Which of the following are not considered by quality planning?

Options:

A.

Contingency budget for remedial work.

B.

Equipment required for quality testing.

C.

Staff qualified to undertake inspections.

D.

Processes to obtain stakeholder approvals.

Discussion
Question 14

The responsibility for development and production of the business case is primarily with:

Options:

A.

the project manager

B.

jointly shared between the project manager and project sponsor.

C.

the project sponsor.

D.

the project steering group/committee.

Discussion
Question 15

Which one Of the following statements about project risk is true?

Options:

A.

Risk is always beneficial to the project.

B.

Risk is neither beneficial or detrimental to the project

C.

Risk can be beneficial or detrimental to the project.

D.

Risk is always detrimental to the project.

Discussion