Question 24

When in the project life cycle should the deployment baseline be formed?

Options:

A.

Deployment phase.

B.

Concept phase.

C.

Definition phase.

D.

Transition phase.

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Dec 6, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Dec 10, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Dec 18, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Dec 22, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 25

Which of the following define leadership?

1) Ability to establish vision and direction

2) Developing team skills that enhance project performance3) Empowering and inspiring people to achieve success

4) Ability to influence and align others towards a common purpose

Options:

A.

1, 2 & 4

B.

1, 2 & 3

C.

2, 3 & 4

D.

1, 3 & 4

Discussion
Question 26

Which of the following phases precedes feasibility in an iterative project life cycle?

Options:

A.

Foundations.

B.

Pre-project.

C.

Concept.

D.

Initiation.

Discussion
Question 27

Which one of the following best describes the purpose of a project's business case?

Options:

A.

A statement of what the project will deliver in terms of products/deliverables and satisfaction.

B.

The reasons why the project sponsor wants their project to proceed.

C.

A statement on how the project fits into the long-term aims of the project sponsor.

D.

Provides justification for undertaking the project, in terms of evaluating the benefits, cost and risks

Discussion