Question 108

Stakeholder analysis considers three aspects for each stakeholder. which are:

Options:

A.

their interest in the project. whether or not they Can influence the project and whether their attitude to the project is for or against.

B.

their level Of technical knowledge. whether or not they are able to act as sponsor and if they are available.

C.

their experience. position in the organizational hierarchy and number Of resources managed

D.

their interest in the project. whether or not they are a member Of the steering group and if they are likely to resist changes.

Discussion
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Nov 23, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Nov 12, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Nov 13, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Nov 2, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Question 109

Which one of the following best defines a benefit?

Options:

A.

A. positive result of stakeholder management.

B.

The successful management of a project.

C.

An improvement resulting from project deliverables.

D.

The successful delivery of project reports and updates.

Discussion
Question 110

One purpose of a typical project business case is to:

Options:

A.

carry out earned value analysis.

B.

allocate resources to the project.

C.

analyse cost-benefit of the project.

D.

plan project work packages

Discussion
Question 111

Which technique could be used by a project manager when resources are limited?

Options:

A.

Resource aggregation.

B.

Resource estimation.

C.

Resource levelling.

D.

Resource expansion

Discussion