Question 76

Options:

A.

Cost Breakdown Structure (CBS) shows costs assigned to:

B.

individual work packages using the Work Breakdown Structure (WBS).

C.

individual resources using the Work Breakdown Structure (WBS).

D.

individual resources using the Responsibility Assignment Matrix (RAM).

E.

individual deliverables using the Responsibility Assignment Matrix (RAM)

Discussion
Question 77

When effectively implemented, what is one of the key roles of governance?

Options:

A.

Provide confidence that the business case is the best option for the current circumstances and that there will be no changes as the project is being delivered.

B.

Provide confidence that the plans that have been developed will guarantee that the project will be delivered on time and to budget.

C.

Provide confidence to all stakeholders that projects are being well managed and the most appropriate financial and technical controls are being exerted.

D Provide confidence to all project team members that their jobs are secure at least from the period of the project start to the handover.

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 15, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Sep 15, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Sep 17, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Sep 3, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 78

Which one of the following best describes stakeholders?

Options:

A.

Anyone who has heard about the project.

B.

Anyone who has an opinion about how the project should be managed.

C.

People wanting to be members of the project team.

D.

People who are affected by the project in some way.

Discussion
Question 79

What is an example of a project management office activity that would be most likely undertaken to support a project?

Options:

A.

Developing the project management plan.

B.

Developing the business case.

C.

Carrying out A. health check.

D Carrying out day-to-day resource management.