Question 84

One of the benefits of developing communication plans in projects is that this ensures:

Options:

A.

the power and influence of stakeholders is understood.

B.

that all communication is delivered face to face.

C.

your message is understood.

D.

clear reporting lines for the project.

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Nov 12, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Nov 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Nov 19, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 4, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 85

For successful risk identification to take place what must the project team know as a minimum?

Options:

A.

Skills of the team delivering the project.

B.

Project objectives.

C.

Amount of time allowed for risk identification to take place.

D.

Location of the venue Where risk identification Will take place

Discussion
Question 86

What is the main benefit of using a risk register in the project?

Options:

A.

It records risks. their impact and the responses being adopted.

B.

It records risk ownership and how issues are being managed.

C.

It assesses the impact and probability of risks taking place.

D.

It directs the team in how the management of risk in the project should be conducted.

Discussion
Question 87

What is a visual representation of a project's planned activity against a calendar called?

Options:

A.

A Gantt chart.

B.

A critical path network.

C.

A product flow diagram.

D.

A Pareto chart.

Discussion
Page: 21 / 30