Question 20

An example Of an external stakeholder group could be:

Options:

A.

users.

B.

A. governmental regulatory body.

C.

functional managers within the sponsoring organisation.

D.

the project team members.

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Sep 22, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Sep 11, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Nia
Why are these Dumps so important for students these days?
Mary Sep 12, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 3, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Question 21

Inspection, measurement and testing to verify that the project outputs meet acceptance criteria is an example of quality:

Options:

A.

reporting.

B.

control.

C.

assurance.

D.

planning.

Discussion
Question 22

At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?

Options:

A.

Storming.

B.

Forming.

C.

Norming.

D.

Performing

Discussion
Question 23

Which of the following are the major stakeholders of the project management plan?

1) Project sponsor

2) General public

3) Project team

4) Project manager

Options:

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4

Discussion
Page: 5 / 30
Title
Questions
Posted

APM-PFQ
PDF

$36.75  $104.99

APM-PFQ Testing Engine

$43.75  $124.99

APM-PFQ PDF + Testing Engine

$57.75  $164.99