Question 120

"The degree of conformance of a process to requirements" is included in the definition of which term?

Options:

A.

Criteria

B.

Compliance

C.

Quality

D.

Benefits

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 14, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Sep 11, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 25, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Sep 4, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Sep 14, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 121

What is one of the most important aspects to establish about a stakeholder's interest in the project?

Options:

A.

If it is positive or negative.

B.

If it is regular or intermittent.

C.

If it is influenced by the project.

D.

If it is influenced by other stakeholders.

Discussion
Question 122

Which of the following is an activity in a typical change control process?

Options:

A.

Recommendation.

B.

Justification.

C.

Planning.

D.

Continuous improvement

Discussion