Question 68

By carrying out a stakeholder analysis, project managers can assess whether or not stakeholders are:

Options:

A.

making unfair judgements.

B.

able to bring expertise to the project team.

C.

in a position to affect their careers.

D.

for or against the project outcomes.

Discussion
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 69

In which phase of the project should the Procurement Strategy be written?

Options:

A.

Concept

B.

Definition

C.

Deployment

D.

Transition

Discussion
Question 70

Which of these is a correct definition of an Estimate?

Options:

A.

The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work

B.

An educated guess that improves over time

C.

A forecast of the probable time or cost of completing work

D.

An estimate is an approximation of project time and cost targets that forms the basis of the contract

Discussion
Question 71

What is the main objective of A. RAM?

Options:

A.

To provide a clear and concise summary of tasks or deliverables and the specific. responsibilities defined.

B.

To provide an outline of the reporting structure to assist in day-to-day management of the project.

C.

To provide an outline of the scope of the project and the specific deliverables that have been agreed for the project.

D.

To provide an outline of the specific costs of the project and which key deliverables they are allocated to.

Discussion