Question 64

Which one of the following does project change control primarily seek to ensure?

Options:

A.

All variance to the project scope is evaluated.

B.

No reduction in the perceived quality of the project outcome.

C.

Management costs of the project do not increase.

D.

Any decrease in the scoped deliverable of the project is rejected.

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jul 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Nia
Why are these Dumps so important for students these days?
Mary Jul 27, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jul 27, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Jul 13, 2025
That's great to know. So, you think new students should buy these dumps?
Question 65

The purpose of project management is to:

Options:

A.

organise management plans.

B.

keep all stakeholders happy.

C.

control change initiatives.

D.

effect beneficial change.

Discussion
Question 66

Which one of the following statements best describes a project?

Options:

A.

A project is a set of tools and techniques often used when delivering organisational change.

B.

A project is the sum of activities needed to remove uncertainty from a unique piece of work.

C.

A unique transient endeavour undertaken to achieve a desired outcome.

D.

A project is a method of planning work.

Discussion
Question 67

Quality control consists of:

1) improvement

2) inspection

3) measurement

4) testing

Options:

A.

1, 2 and 4

B.

2, 3 and 4

C.

1, 3 and 4

D.

1, 2 and 3

Discussion