Question 20

Which type of risk diagram is useful for showing time ordering of events?

Options:

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Jul 11, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Robin
Cramkey is highly recommended.
Jonah Jul 28, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jul 13, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Nell
Are these dumps reliable?
Ernie Jul 13, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Jul 23, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 21

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Options:

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Discussion
Question 22

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Discussion
Question 23

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Discussion