Question 80

The following is a network diagram for a project.

Questions 80

The free float for Activity H is how many days?

Options:

A.

4

B.

5

C.

10

D.

11

Discussion
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Dec 15, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Dec 19, 2025
Great. Yes they are really effective
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Dec 14, 2025
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Dec 22, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 81

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Discussion
Question 82

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

Options:

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Discussion
Question 83

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Discussion
Page: 20 / 97
Title
Questions
Posted

CAPM
PDF

$26.25  $104.99

CAPM Testing Engine

$31.25  $124.99

CAPM PDF + Testing Engine

$41.25  $164.99