Question 188

What is a tool or technique used in the Control Quality process?

Options:

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Discussion
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Sep 2, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Sep 17, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Sep 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Sep 18, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 189

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Discussion
Question 190

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Discussion
Question 191

How can a project manager evaluate project team development?

Options:

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

Discussion