Question 96

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

Options:

A.

Develop consensus among stakeholders

B.

Get the budget approved for change

C.

Make sure management is aware of the change

D.

Get approval from the change control board

Discussion
Question 97

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Discussion
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Sep 10, 2026
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Sep 22, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 23, 2026
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Sep 9, 2026
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Question 98

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

Options:

A.

USS-30,000

B.

US$120,000

C.

US$370,000

D.

US$400,000

Discussion
Question 99

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair