Question 96

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Discussion
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Oct 18, 2025
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Oct 3, 2025
did you use PDF or Engine? Which one is most useful?
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Oct 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Question 97

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Discussion
Question 98

The following chart contains information about the tasks in a project.

Questions 98

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Discussion
Question 99

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Discussion
Page: 24 / 97
Title
Questions
Posted

CAPM
PDF

$36.75  $104.99

CAPM Testing Engine

$43.75  $124.99

CAPM PDF + Testing Engine

$57.75  $164.99