During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
If a project manager effectively manages project knowledge, a key benefits is that: