Question 96

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Discussion
Question 97

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Discussion
Neve
Will I be able to achieve success after using these dumps?
Rohan Dec 16, 2025
Absolutely. It's a great way to increase your chances of success.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Dec 20, 2025
That's great to know. So, you think new students should buy these dumps?
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Dec 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 98

The following chart contains information about the tasks in a project.

Questions 98

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Discussion
Question 99

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget