Question 44

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Dec 18, 2025
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Dec 28, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Dec 24, 2025
YES….. I saw the same questions in the exam.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Dec 15, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Dec 15, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Question 45

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Discussion
Question 46

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Discussion
Question 47

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Discussion