Exam Name: | Certified Associate in Project Management (CAPM) | ||
Exam Code: | CAPM Dumps | ||
Vendor: | PMI | Certification: | CAPM |
Questions: | 1250 Q&A's | Shared By: | orlagh |
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?