Question 12

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Discussion
Question 13

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Discussion
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Dec 18, 2025
did you use PDF or Engine? Which one is most useful?
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Dec 5, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Dec 16, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 14

Which tool or technique is used in Close Procurements?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Discussion
Question 15

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Discussion
Page: 3 / 97
Title
Questions
Posted

CAPM
PDF

$26.25  $104.99

CAPM Testing Engine

$31.25  $124.99

CAPM PDF + Testing Engine

$41.25  $164.99