Question 192

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

Options:

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Dec 20, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Dec 18, 2025
did you use PDF or Engine? Which one is most useful?
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Dec 15, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Dec 1, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 193

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

Options:

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

Discussion
Question 194

It you established a contingency reserve including time, money, and resources, how are you handling risk?

Options:

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Discussion
Question 195

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Options:

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Discussion