Question 104

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Dec 20, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Dec 2, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Question 105

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Discussion
Question 106

The following chart contains information about the tasks in a project.

Questions 106

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Discussion
Question 107

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Discussion