Question 52

What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational Breakdown Structure (OBS)

B.

Work Performance Information

C.

Work Package

D.

Work Breakdown Structure (WBS)

Discussion
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis (not set)
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Neve
Will I be able to achieve success after using these dumps?
Rohan (not set)
Absolutely. It's a great way to increase your chances of success.
Andrew
Are these dumps helpful?
Jeremiah (not set)
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka (not set)
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 53

The ability to achieve cost savings is inversely proportional to _____.

Options:

A.

empowerment to the P.M.

B.

productivity

C.

the estimated costs to complete

D.

the earned value achieved to date

E.

None of the other alternatives apply.

Discussion
Question 54

The critical path in a schedule network is the path that:

Options:

A.

Takes the longest time to complete

B.

Allows some flexibility in scheduling a start time.

C.

Is not affected by schedule slippage

D.

Must be done before any other tasks

E.

All of the other alternatives apply.

Discussion
Question 55

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?

Options:

A.

Bottom-up estimating

B.

Analogous estimating

C.

Parametric estimating

D.

Three-point estimates

Discussion