Question 44

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers. You performed this project under contract.

You are in the Closing process and know that product verification is for what purpose?

Options:

A.

To verify that all the work was completed correctly and satisfactorily

B.

To evaluate project goals and ensure that the product of the project meets the requirements

C.

To verify the goals of the project and ensure that the product of the project is complete

D.

To evaluate all the work of the project and compare the results to project scope

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Nov 11, 2025
That's great to hear. I am going to try them soon.
Nell
Are these dumps reliable?
Ernie Nov 23, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Nov 14, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Neve
Will I be able to achieve success after using these dumps?
Rohan Nov 20, 2025
Absolutely. It's a great way to increase your chances of success.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Nov 19, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 45

What information does the stakeholder register contain?

Options:

A.

Communication model

B.

Identification information

C.

Communication method

D.

Identification plan

Discussion
Question 46

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope.

Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Discussion
Question 47

Who has the cost risk in a fixed price (FP) contract?

Options:

A.

The team

B.

The buyer

C.

The seller

D.

Management

Discussion