Question 44

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers. You performed this project under contract.

You are in the Closing process and know that product verification is for what purpose?

Options:

A.

To verify that all the work was completed correctly and satisfactorily

B.

To evaluate project goals and ensure that the product of the project meets the requirements

C.

To verify the goals of the project and ensure that the product of the project is complete

D.

To evaluate all the work of the project and compare the results to project scope

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Aug 31, 2024
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Question 45

What information does the stakeholder register contain?

Options:

A.

Communication model

B.

Identification information

C.

Communication method

D.

Identification plan

Discussion
Question 46

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope.

Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Discussion
Question 47

Who has the cost risk in a fixed price (FP) contract?

Options:

A.

The team

B.

The buyer

C.

The seller

D.

Management

Discussion