Question 24

A problem occurs on an activity with free float and the project manager has extended its duration.

What is MOST likely to be affected?

Options:

A.

Project duration

B.

Resource schedules

C.

Project scope management plan

D.

The latest start for the successor activity

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Oct 16, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Oct 8, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Oct 10, 2025
That's great to know. So, you think new students should buy these dumps?
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Oct 6, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Oct 13, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Question 25

You are the project manager of a project. You have just completed the Collect Requirements and Define Scope.

What should you do next?

Options:

A.

Control Scope

B.

Create WBS

C.

Value analysis

D.

Verify Scope

Discussion
Question 26

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.

You should calculate the forecast using which of the following methods?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Discussion
Question 27

All of the following are inputs to the quality process EXCEPT:

Options:

A.

Organizational process assets.

B.

Checklists.

C.

Quality policy.

D.

The project scope statement.

Discussion