Question 24

A problem occurs on an activity with free float and the project manager has extended its duration.

What is MOST likely to be affected?

Options:

A.

Project duration

B.

Resource schedules

C.

Project scope management plan

D.

The latest start for the successor activity

Discussion
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Oct 26, 2026
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Inaaya
Are these Dumps worth buying?
Fraser Oct 11, 2026
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 20, 2026
They give you a competitive edge and help you prepare better.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 19, 2026
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Question 25

You are the project manager of a project. You have just completed the Collect Requirements and Define Scope.

What should you do next?

Options:

A.

Control Scope

B.

Create WBS

C.

Value analysis

D.

Verify Scope

Discussion
Question 26

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.

You should calculate the forecast using which of the following methods?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Discussion
Question 27

All of the following are inputs to the quality process EXCEPT:

Options:

A.

Organizational process assets.

B.

Checklists.

C.

Quality policy.

D.

The project scope statement.

Discussion