Question 36

Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships.

What is the total float on path BEG?

Options:

A.

0

B.

1

C.

2

D.

3

Discussion
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 37

You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process group. You've published the scope statement and scope management plan.

The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and who will prepare it is which of the following?

Options:

A.

Scope management plan

B.

Project charter

C.

Communications management plan

D.

Information distribution plan

Discussion
Question 38

Scope verification is PRIMARILY concerned with which of the following?

Options:

A.

Acceptance of the work deliverables.

B.

Accuracy of the work deliverables.

C.

Approval of the scope statement.

D.

Accuracy of the work breakdown structure.

Discussion
Question 39

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Discussion