Question 80

Which of the following is not true for a Responsibility Assignment Matrix (RAM)?

Options:

A.

Defines what project member is responsible for each activity

B.

Defines all people associated with each activity

C.

Defines responsibilities for each WBS component

D.

All of the other alternatives apply

Discussion
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 19, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Nov 26, 2025
Thanks for the recommendation! I'll check it out.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Nov 3, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Nov 9, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Nov 11, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 81

Advantages of the functional (hierarchical) form of organization include _____ and creation of technical competence.

Options:

A.

Single voice to customers

B.

High information processing capability

C.

Ease of horizontal coordination

D.

Clearly defined authority

Discussion
Question 82

All of the following are tools and techniques of the Contract Administration process except for which one?

Options:

A.

Contract change control system, buyer-conducted performance review, and inspections and audits

B.

Records management system and information technology

C.

Contract performance information gathering and contract reporting systems

D.

Performance reporting, payment system, and claims administration

Discussion
Question 83

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Qualitative risk analysis

B.

Quantitative risk analysis

C.

Risk management planning

D.

Risk response planning

Discussion