Question 84

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

Options:

A.

Both 1) conceptual, and 2) post project evaluation

B.

cut-over

C.

conceptual

D.

execution

E.

post project evaluation

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 3, 2024
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 85

Project scope statement and resource calendars are inputs to what Project Time Management process?

Options:

A.

Activity Sequencing

B.

Activity Resource Estimating

C.

Schedule Development

D.

Schedule Control

Discussion
Question 86

Which of the following is the LEAST effective way to influence the factors that create changes to the cost baseline?

Options:

A.

Review the project scope with the functional manager responsible for the greatest number of requested changes.

B.

Explain to those requesting changes the negative impact of change to the project.

C.

Eliminate the scope causing the most changes.

D.

Notify all stakeholders that no more changes will be allowed.

Discussion
Question 87

Which of the following provides a standardized, effective, and efficient way to centrally manage approved changes and baselines within a project?

Options:

A.

Project management information system

B.

Configuration management system

C.

Change control board

D.

Project management plan

Discussion