To help you prepare for the PSP AACE International exam, we are offering free PSP AACE International exam questions. All you need to do is sign up, provide your details, and prepare with the free PSP practice questions. Once you have done that, you will have access to the entire pool of Planning & Scheduling Professional (PSP) Exam PSP test questions which will help you better prepare for the exam. Additionally, you can also find a range of Planning & Scheduling Professional (PSP) Exam resources online to help you better understand the topics covered on the exam, such as Planning & Scheduling Professional (PSP) Exam PSP video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic AACE International PSP exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

Options:

A.  

Avoiding a late delivery penalty from the owner

B.  

Maximizing the $500,000 bonus

C.  

Avoiding the 2023-2024 winter/wet weather season

D.  

Minimizing the indirect expenditure chargeable to the contractor

Discussion 0
Questions 3

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Questions 3

Options:

A.  

11 Mar 2024

B.  

21 Mar 2024

C.  

19 Feb 2024

D.  

20 Mar 2024

Discussion 0
Questions 4

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

Options:

A.  

Using the critical chain method

B.  

Fast tracking

C.  

Crashing

D.  

Rebaseline the project

Discussion 0
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Nov 7, 2025
That's great. I think I'll give Cramkey Dumps a try.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Nov 7, 2025
Me too. They're a lifesaver!
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Nov 2, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Nov 4, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Questions 5

For which of these delays should an owner grant a time extension?

Options:

A.  

Structural steel shop drawings.

B.  

Shop drawings and centrifuge delay.

C.  

Differing site conditions at parking structure.

D.  

Differing site conditions and centrifuge delay.

Discussion 0