Question 44

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

Options:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

Discussion
Nell
Are these dumps reliable?
Ernie Sep 4, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Robin
Cramkey is highly recommended.
Jonah Sep 1, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Sep 17, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 7, 2025
Thanks for the recommendation! I'll check it out.
Question 45

Determine the correct formula and date for the late start for the Activity 11001:

Questions 45

Options:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Discussion
Question 46

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

Options:

A.

All managers should be encouraged to review contiguous activity status

B.

The process of each activity should be indicated by the responsible manager

C.

The critical path should not be revisited to ensure all the downstream logic and durations are still accurate

D.

The project team should be asked to review status for accuracy

Discussion
Question 47

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Discussion