Question 24

What is the free float for Activity F?

Questions 24

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Discussion
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Jan 23, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Jan 12, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Jan 26, 2026
Me too. They're a lifesaver!
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Jan 22, 2026
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 25

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

Questions 25

Options:

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Discussion
Question 26

Identify the late finish to develop plans and specs.

Questions 26

Options:

A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Discussion
Question 27

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Questions 27

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Discussion