Question 24

What is the free float for Activity F?

Questions 24

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Discussion
Question 25

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

Questions 25

Options:

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Discussion
Question 26

Identify the late finish to develop plans and specs.

Questions 26

Options:

A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 3, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Nov 11, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Nov 25, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Nov 7, 2025
That's great. I think I'll give Cramkey Dumps a try.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Nov 13, 2025
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Question 27

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Questions 27

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.