AACE International PSP Exam Overview :

Exam Name: Planning & Scheduling Professional (PSP) Exam
Exam Code: PSP Dumps
Vendor: AACE International Certification: Professional Level Certifications
Questions: 216 Q&A's Shared By: avery
Question 8

What changes to logic would eliminate Activity B from the critical path?

Options:

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Feb 25, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Feb 14, 2026
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Feb 13, 2026
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Feb 21, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 9

Determine the correct formula and date for the late finish for Activity 2001.

Questions 9

Options:

A.

LF.2001 - 1 day -> 08-28-01.

B.

LS.2002- 1 day-> 08-29-01.

C.

LS.2002 + 1 day -> 08-30-01.

D.

LS.2002 - 1 day -> 08-28-01.

Discussion
Question 10

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Discussion
Question 11

The best source of project risk or opportunities is:

Options:

A.

A similar project in another state

B.

Rumors from the local Chamber of Commerce

C.

Failures by other contractors

D.

Internal and external stakeholders

Discussion