AACE International Updated PSP Exam Questions and Answers by nel

Page: 13 / 15

AACE International PSP Exam Overview :

Exam Name: Planning & Scheduling Professional (PSP) Exam
Exam Code: PSP Dumps
Vendor: AACE International Certification: Professional Level Certifications
Questions: 216 Q&A's Shared By: nel
Question 52

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Options:

A.

42.

B.

36.

C.

40.

D.

37.

Discussion
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Jan 4, 2026
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Jan 6, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Inaaya
Are these Dumps worth buying?
Fraser Jan 15, 2026
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jan 26, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Jan 23, 2026
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 53

Activity C is a

Options:

A.

Contentious activity.

B.

Continuous activity.

C.

1-day activity.

D.

Milestone.

Discussion
Question 54

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

Options:

A.

30 lifts

B.

133 lifts

C.

42 lifts

D.

60 lifts

Discussion
Question 55

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

Options:

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

Discussion