Question 28

What is the cycle time?

Questions 28

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Discussion
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 26, 2024
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Aug 27, 2024
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Question 29

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Discussion
Question 30

What is the free float for Activity F?

Questions 30

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Discussion
Question 31

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Discussion