AACE International PSP Exam Overview :

Exam Name: Planning & Scheduling Professional (PSP) Exam
Exam Code: PSP Dumps
Vendor: AACE International Certification: Professional Level
Questions: 163 Q&A's Shared By: fearne
Question 28

What is the cycle time?

Questions 28

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Discussion
Nia
Why are these Dumps so important for students these days?
Mary Jul 27, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Jul 28, 2025
did you use PDF or Engine? Which one is most useful?
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jul 27, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Jul 16, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Jul 15, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 29

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Discussion
Question 30

What is the free float for Activity F?

Questions 30

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Discussion
Question 31

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path