You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?