| Exam Name: | Planning & Scheduling Professional (PSP) Exam | ||
| Exam Code: | PSP Dumps | ||
| Vendor: | AACE International | Certification: | Professional Level Certifications | 
| Questions: | 216 Q&A's | Shared By: | lowen | 
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?
The schedule or budget at completion less the estimate at completion is___________.