Question 88

Which of the following is a source reduction strategy to eliminate waste produced by a project?

Options:

A.

Custom design

B.

Design-build

C.

Material science

D.

Prefabrication

Discussion
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Question 89

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite,

Storage and Collection of Recyclables?

Options:

A.

Take appropriate measures for the safe collection, storage and disposal of batteries

B.

Make a waste stream projection for the entire year based on the six hours of the waste stream study

C.

Make a waste stream projection for the entire week, based on the six hours of the waste stream study

D.

Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Discussion
Question 90

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Discussion
Question 91

One point can be achieved through Sustainable Sites Credit, Heat Island Reduction by providing:

Options:

A.

Preferred parking for green vehicles

B.

A minimum of 75% of parking spaces under cover

C.

Access to public transportation stops

D.

A roof with artificial turf grass

Discussion