Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

IIA Updated IIA-CIA-Part2 Exam Questions and Answers by kade

Page: 2 / 55

IIA IIA-CIA-Part2 Exam Overview :

Exam Name: Internal Audit Engagement
Exam Code: IIA-CIA-Part2 Dumps
Vendor: IIA Certification: CIA
Questions: 747 Q&A's Shared By: kade
Question 8

An internal audit team leader is having difficulties completing the planning phase of an assurance engagement because the business unit lacks a system of internal controls. Which of the following is the most appropriate course of action for the internal audit team leader?

Options:

A.

Defer the engagement until a system of internal control has been established

B.

Change the scheduled engagement from assurance to consulting to help correct the shortcomings

C.

Add a consulting component to the already scheduled assurance engagement

D.

Seek the involvement of the external auditor to assist with improving the internal controls

Discussion
Question 9

When me internal audit activity does not have sufficient time to complete its usual root cause analysis which c4 the following is most appropriate?

Options:

A.

The chief audit executive may recommend that management conduct further work to identify the root cause and address the issue

B.

Internal auditors should finish the engagement without conducting the root cause analysis and draft the audit report, though the report would not be considered complete until the analysis is concluded

C.

internal auditors must adjust their future engagement schedule to ensure that the root cause analysis is always performed before the engagement is concluded

D.

Internal auditors should Instead perform a Pareto rule analysis

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Mar 12, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Mar 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Mar 18, 2026
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Mar 14, 2026
Yeah, definitely. I experienced the same.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Mar 27, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 10

An organization's finance manager plans to implement a state-of-the-art management system to better manage the organization's receivables. The finance manager consulted the chief audit executive (CAE) and asked for her assistance in determining whether the organization is able to accommodate this system. How would the CAE proceed to determine the objectives of this engagement

Options:

A.

Ask the CEO to determine the scope and objectives of the engagement

B.

Request that the board disclose its concerns over governance for inclusion in the engagement

C.

Discuss the concerns with the finance manager and work together to agree on the engagement objectives

D.

Review previous audit reports from the area and develop engagement objectives to address the area's key risks and controls

Discussion
Question 11

Which of the following statements describes an engagement planning best practice?

Options:

A.

It is best to determine planning activities on a case-by-case basis because they can vary widely from engagement to engagement.

B.

If the engagement subject matter is not unique, it is not necessary to outline specific testing procedures during the planning phase.

C.

The engagement plan includes the expected distribution of the audit results, which should be kept confidential until the audit report is final.

D.

Engagement planning activities include setting engagement objectives that align with audit client's business objectives.

Discussion
Page: 2 / 55
Title
Questions
Posted

IIA-CIA-Part2
PDF

$36.75  $104.99

IIA-CIA-Part2 Testing Engine

$43.75  $124.99

IIA-CIA-Part2 PDF + Testing Engine

$57.75  $164.99