Question 48

What is the purpose of a Product Status Account?

Options:

A.

A set of records that describe information about the project

B.

A log used to record problems or concerns about products

C.

An audit or review to compare actual status of products

D.

A report covering the status about the state of the projects products within

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Dec 17, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Dec 20, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Dec 18, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 49

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?

Options:

A.

The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.

B.

The MFH Quality Manager should only administer the configuration management procedure on one project at a time. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.

C.

The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.

Discussion
Question 50

QUALITY

Here are three actions related to managing quality on the Health and Safety Training Project.

Which role (A-F) should be responsible for each action?

Choose only one role for each action. Each role can be used once, more than once, or not at all.

Questions 50

Options:

Discussion
Question 51

STARTING UP A PROJECT

Here are three actions carried out by the project manager during the ‘starting up a project’ process.

As part of which activity (A-F) should each action be carried out?

Choose only one activity for each action. Each activity can be used once, more than once, or not at all.

Questions 51

Options:

Discussion
Page: 12 / 19
Title
Questions
Posted

Prince2-Practitioner
PDF

$26.25  $104.99

Prince2-Practitioner Testing Engine

$31.25  $124.99

Prince2-Practitioner PDF + Testing Engine

$41.25  $164.99