New Year Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

PRINCE2 Updated Prince2-Practitioner Exam Questions and Answers by quinn

Page: 7 / 9

PRINCE2 Prince2-Practitioner Exam Overview :

Exam Name: PRINCE2 Practitioner Exam
Exam Code: Prince2-Practitioner Dumps
Vendor: PRINCE2 Certification: PRINCE2 Certification
Questions: 282 Q&A's Shared By: quinn
Question 28

Which statement is an appropriate entry for the outline Business Case heading within the Project Brief?

Options:

A.

10-year service contract should be agreed with the selected service provider.

B.

External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits.

C.

The project will run for two years and the benefits will be realized over 1a years.

D.

The project should be split into four management stages.

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Nov 19, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Nov 11, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Nov 2, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Nov 1, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Nov 18, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 29

While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log.

Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?

Options:

A.

MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.

B.

The Project Brief is a complex document and may not be approved by the Executive.

C.

There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.

Discussion
Question 30

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Questions 30

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

Which statement applies to the Communication procedure section?

Options:

A.

No change to entry 2 because this is a sufficient description of the process required.

B.

Amend entry 2 to include MNO Manufacturing Company standards for both internal and external company communications.

C.

Delete entry 2 because only variations from the MNO Manufacturing Company standards should be recorded here.

Discussion
Question 31

Which of the following principles describes this statement?

"xxx defines tolerances for each project objective to establish limits of delegated authority"

Options:

A.

Manage by stages

B.

Focus on products

C.

Manage by exception

D.

Learn from experience

Discussion
Page: 7 / 9

Prince2-Practitioner
PDF

$26.25  $104.99

Prince2-Practitioner Testing Engine

$31.25  $124.99

Prince2-Practitioner PDF + Testing Engine

$41.25  $164.99