Question 72

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

Options:

A.

Scope, People & Resources, Benefit

B.

Scope, Risk, Product

C.

Risk, Benefit, Product

D.

Scope, Risk, Benefit

Discussion
Question 73

Which of the following activities could trigger the production of an exception plan?

Options:

A.

Review Stage status

B.

Giving ad hoc direction

C.

Escalating a project issue

D.

Report stage end

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Aug 11, 2026
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Aug 24, 2026
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Aug 4, 2026
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Aug 20, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Question 74

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Questions 74

Options:

Discussion
Question 75

Which of the following activities is NOT an action of preparing for planned closure?

Options:

A.

Update the project plan with actual

B.

Update the Project Management Team

C.

Request a product status account

D.

Confirm project has delivered what is defined in Project Product Description

Discussion
Page: 18 / 19
Title
Questions
Posted

Prince2-Practitioner
PDF

$36.75  $104.99

Prince2-Practitioner Testing Engine

$43.75  $124.99

Prince2-Practitioner PDF + Testing Engine

$57.75  $164.99