| Exam Name: | PRINCE2 7 Practitioner (7th Edition) Exam | ||
| Exam Code: | Prince2-Practitioner Dumps | ||
| Vendor: | PRINCE2 | Certification: | PRINCE2 Certification |
| Questions: | 263 Q&A's | Shared By: | safaa |
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
Which of the following activities could trigger the production of an exception plan?
The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Which of the following activities is NOT an action of preparing for planned closure?