Question 52

The project executive delegates assurance of sustainability targets to the Sustainability Manager from the portfolio office.

Is this an appropriate application of the organization practice, and why?

Options:

A.

Yes, to support manage by exception

B.

Yes, because assurance may be delegated to someone with expertise

C.

No, because the executive must do assurance personally

D.

No, because accountability cannot be delegated

Discussion
Question 53

The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.

Is this appropriate, and why?

Options:

A.

Yes, because the project should verify that the recorded status reflects the actual status of the products.

B.

Yes, because the change control approach should specify how the configuration item records are approved.

C.

No, because the project manager should ensure that the change control approach is tailored to the project.

D.

No, because the issue management and change control procedures can be treated as separate, but related, procedures.

Discussion
Question 54

The project is part of a program to develop more training courses that respond to new legislation. The project manager has requested that project support be made available from the program. As a result, the executive has confirmed that this will be carried out by the program office.

Is this appropriate, and why?

Options:

A.

Yes, because the program office should provide support to projects, if requested.

B.

Yes, because the project support role is not optional and must be provided.

C.

No, because the project manager should take on project support responsibilities.

D.

No, because program and project team structures need to be separate.

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse May 12, 2026
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik May 10, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis May 19, 2026
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Ayra
How these dumps are necessary for passing the certification exam?
Damian May 8, 2026
They give you a competitive edge and help you prepare better.
Question 55

BUSINESS CASE

Here are three statements from the business case for the Health and Safety Project.

Under which heading in the business case (A-F) should they be recorded?

Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.

Questions 55

Options:

Discussion
Page: 13 / 19
Title
Questions
Posted

Prince2-Practitioner
PDF

$36.75  $104.99

Prince2-Practitioner Testing Engine

$43.75  $124.99

Prince2-Practitioner PDF + Testing Engine

$57.75  $164.99