PRINCE2 Updated Prince2-Practitioner Exam Questions and Answers by rosalie

Page: 10 / 19

PRINCE2 Prince2-Practitioner Exam Overview :

Exam Name: PRINCE2 7 Practitioner (7th Edition) Exam
Exam Code: Prince2-Practitioner Dumps
Vendor: PRINCE2 Certification: PRINCE2 Certification
Questions: 293 Q&A's Shared By: rosalie
Question 40

Scenario

Additional Information

Product Description

Questions 40

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

The service level agreement contains a number of technical terms that are missing from its glossary of terms.

Options:

A.

Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days’ tolerance.

B.

Raise an issue (off-specification).

C.

Raise an issue (request for change).

D.

No action required.

Discussion
Question 41

Which principle is central to the quality theme and provides explicit understanding of what the project will create?

Options:

A.

Manage by stages

B.

Focus on products

C.

Manage by exception

D.

Learn from experience

Discussion
Question 42

Scenario

Extract from the Project Product Description (with errors)

Questions 42

Which 2 statements apply to the Derivation section?

Options:

A.

Move entry 9 to Composition because this is within the scope of the project.

B.

Delete entry 10 because this is NOT a source product for this project.

C.

Delete entry 11 as this is already correctly shown under Development Skills required.

D.

Move entry 12 to Composition, because this is within the scope of this project.

E.

Add 'Professional photographer'.

Discussion
Question 43

In which strategy would the change control process be recorded?

Options:

A.

Quality Management Strategy

B.

Configuration Management Strategy

C.

Risk Management Strategy

D.

Communication Management Strategy

Discussion
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Aug 13, 2026
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Inaaya
Are these Dumps worth buying?
Fraser Aug 2, 2026
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Aug 5, 2026
YES….. I saw the same questions in the exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Aug 17, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Aug 3, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Page: 10 / 19
Title
Questions
Posted

Prince2-Practitioner
PDF

$36.75  $104.99

Prince2-Practitioner Testing Engine

$43.75  $124.99

Prince2-Practitioner PDF + Testing Engine

$57.75  $164.99