Question 112

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Discussion
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate (not set)
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Andrew
Are these dumps helpful?
Jeremiah (not set)
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie (not set)
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie (not set)
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 113

In which of the following types of organizations is resource availability moderate to high?

Options:

A.

Weak matrix

B.

Balanced matrix

C.

Strong matrix

D.

Projectized

Discussion
Question 114

Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Discussion
Question 115

Organizational process assets can be divided into which of the following two categories?

Options:

A.

Project files and corporate knowledge base

B.

Templates, and processes and procedures

C.

Standards, and processes and procedures

D.

Corporate knowledge base and processes and procedures

Discussion
Page: 28 / 34
Title
Questions
Posted

PMI-001
PDF

$35  $99.99

PMI-001 Testing Engine

$42  $119.99

PMI-001 PDF + Testing Engine

$56  $159.99