Question 12

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Jan 2, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Jan 4, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Jan 19, 2026
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Jan 22, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Question 13

Taking out insurance in relation to risk management is called what?

Options:

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Discussion
Question 14

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Discussion
Question 15

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Discussion